MISO selects AEP-Berkshire JV to build $1.2B, 765-kV transmission project
Key Takeaway
MISO's award of $1.55 billion in new transmission projects underscores significant grid expansion and a focus on cost-effective development, creating opportunities for developers and improving service for large loads.
AI Summary
- •MISO awarded two major transmission projects totaling $1.55 billion: a $1.2B, 765-kV project to AEP-Berkshire JV and a $350M project in Wisconsin to Viridon.
- •Viridon's selection was explicitly based on its commitment to cost containment, signaling a key competitive factor for future infrastructure bids in MISO.
- •These significant transmission investments indicate MISO's ongoing grid expansion efforts, which can improve reliability and facilitate new generation interconnections and large load development.